VENT SHAFT #13

Conventional Shaft Sinking was recently completed at CONSOL Energy's Buchanan Mine. The scope of work includes:

  • (1) Ventilation Shaft
  • 1,837 VF
  • 22-ft. Diameter
  • Concrete-Lined
  • Dual Compartments
  • Shotcreted 4-Way Station




Services/Methods Performed:

FAST FACTS:

LOCATION: Richlands, VA

MARKET: Coal

OWNER: CONSOL Energy

MINE: Buchanan Mine

CONTRACTOR: Frontier-Kemper Constructors, Inc.

START DATE: July 2014

END DATE: July 2015